Circuit Flat Bridge and Bucketty Culvert

The History of the Bridge

Old Picture of Bridge

This bridge was built probably built in 1831-2 by Arnold Clares bridge Party, after they had completed the bridges at Sampsons Pass and near Ten Mile Hollow. It comprises two stone abutments originally 14.6 metres in length, 8.5 m wide, up to 2.7 m high and with a span of 2.75 metres. It is the most refined single span bridge on the Road. Projecting buttresses flank each corner and there are seven stone corbels which project from each abutment and would have supported struts for the original decking. The extensive flanking walls retain part of a coping course below a single course of capping stones. The bridge remained sufficiently intact to still be in use in the 1920s, as the accompanying photo suggests.

Members near bridge

By the 1970s, however, the decking was gone, and only a few support timbers remained. In 1986 when this photo was taken, only one of the timbers remained. Bushfires may well have burned out the decking. During the decades of the 1970s and 80s traffic was using this section of the Road - it provided access to the western site of Mangrove Creek dam during its construction. 4WD enthusiasts were also exploring the great North Road through here, often using it as an "adventure road" to test the capabilities of their vehicles.

Damaged Bridge

In the 1980s the NPWS removed some of the bridge stones from the creek gully and took them to the Bucketty Depot for safe keeping. During the 1990s the gully through and below the bridge became further eroded - the lack of vegetation meant that soil was washed away. By the mid 1990s, the soil level on the downstream side of the bridge was 60-75 mm lower than it had been 15 years earlier. Water was in danger of eroding the bridge walling. One downstream buttress had been severely damaged through removal of several layers of stone, and some stones had been removed from its opposite buttress. The capping stones and some of the coping from southern upstream walling had also been removed.

Erosion of Bridge

The continuing erosion on the downstream side of the bridge was threatening its foundations and the loss of the stones on the corner buttresses was allowing water into the bridge foundations. The buttresses were no longer able to provide adequate support for the bridge walling. Trees had established themselves in the road surface, and near the stone walls and as they grew they were starting to dislodge stones. Since the decking was no longer intact, vehicles developed a track immediately downstream of the bridge - the gully was not deep - but after rain, it became gradually more and more eroded.

Sometimes vehicles became stuck in the eroded creek-bed. People removed stones from the walling of the bridge to fill in the gully so they could traverse it. These stones were invariably crushed under the weight of heavy vehicles, as can be seen to the right of the wall buttress.

St Heliers Prison Crew and the Stonemason to the rescue

Team Collecting Rocks

In February 1998 the Convict Trail Project organised the prison crew from St Heliers to do some work on the bridge. They removed tree growth from the bridge, and retrieved 16 stones from the creekbed below the bridge. Local stonemason Albert Kraan was then engaged by the Convict Trail Project to replace the missing stones on the bridge buttresses. As well as re-using as many of the retrieved stones (and those from the Bucketty depot) he obtained additional stones from the quarry where the original stone from the bridge had been quarried. The prisoners opened an access route along an old disused timber-logging track, so Albert could get his truck to the site. After he had sufficient stone, they closed off vehicular access to the quarry again.

The erosion problem remained, so the Convict Trail then negotiated with Gosford Council (who technically are responsible for the bridge) and the NPWS, (as the bridge adjoins Yengo National Park,) to undertake necessary and urgently required repairs to the eroded area on the downstream side of the bridge. Gosford Council provided the materials, the NPWS provided their works supervisor and equipment such as a truck and bulldozer, and the Convict Trail again obtained the services of the prison crew from St Heliers to undertake the heavy work. The work was done in February 1999, starting with the closure of the vehicular access alonside the bridge area. A detour route existed upstream of the bridge. This was tidied up with appropriate signs to indicate in an obvious fashion that traffic should not try to open the eroded downstream side.

Bridge Road Sign Construction Roadway

Gabian baskets were installed in the creek gully about 4 metres away from the bridge, and the soil built up around them. The eroded areas between the bridge and the baskets were filled, and smoothed out, and additional erosion measures were installed. The following photographs show how the work was performed and what it looked like when it was finished.

Construction area with people Laying Mesh
Digging Construction of small wall
Preparing area for concrete Further preparation

Rye-grass seed was scattered, to encourage immediate revegetation of the rehabilitated area, as it would allow other seeds to settle and germinate, but would not seed itself and spread into the natural bush. Repair of the stone work is visible on both buttresses. Telegraph poles (top left of picture) were placed across the top of this section of the bridge road to stop vehicular access. There had always been an alternative access route upstream of the bridge. It has been made more obvious so that traffic would not need to try to re-open the eroded side. The area still looks a bit open in the picture taken in March 1999 but it is gradually regenerating.

The NPWS have now put additional interpretation plaque at this site.

Restored Bridge

Bucketty Culvert

Bucketty Before

Bucketty culvert before reconstruction showing dropping broken capping stone and pipe extension on far side.

The Culvert was constructed between 1830-31 by No. 29 Road Party who were stationed at Dennis Dog Kennel. Sometime after 1965 and before 1983 a large section of this culvert collapsed and stone was removed, possibly to fill in round the pipe that was put into the Bridge space a few hundred meters to the north of the culvert. In 2002 the Convict Trail Project received a dollar for dollar grant from the NSW Heritage Office for the restoration of this culvert. The labour from the St Heliers MOP provided the Convict Trail Project with their dollar contribution. The prisoners carefully deconstructed the culvert and hand excavated the area that had to be excavated and then worked with the stonemason Ken Fletcher of Wollombi Stonemasonary Sevices to reconstruct the culvert. The Newcastle Herald visited the site and ran a story about the Stonemason and prisoners work together. One of the outcomes of the project was one of the prisoners a young local man (who was due for release just after the project finished) worked casually for the stonemason as a labourer while waiting to get a job in his own trade. This was the last job where the St Heliers MOP worked with the Convict Trail Project. They were to come back to do the landscaping but unfortunately the overseer died before this happened. The local community rallied and in a large working bee completed the landscaping.

The Convict Trail Project with the help of the local community has installed a seat at Bucketty Culvert in memory of the overseer and in appreciation of his large contribution to Convict Trail Project. The seat was made from a 1830s convict hewn culvert capping stone. As the stone was flawed it could not be reused in the reconstruction.

The MOP overseer

The MOP Overseer and the Stone Mason Ken Fletcher watch the MOP carefully deconstruct the wing wall at Bucketty Culvert

St Heliers MOP

St Heliers MOP excavating at Bucketty Culvert

Droppings

One of the MOP crew found these droppings in a 50 mm diameter hole in the excavation behind the wing wall. There was much speculation as to what sort of animal they were from, they were identified as Beetle or Insect Lave frass. The pellets were approximately 4 mm wide and 2 mm thick of varying lengths.

Stone mason

Stone mason and Prisoners work together at Bucketty culvert

Cutting the Stones

Stonemasons Israel and Nehemiah Fletcher cutting new corner stones with hand tools.

Cutting the Stones

Reconstruction before landscaping

Drawing showing original work

Drawing on interpretative signage installed at Bucketty Culvert showing original work in the new structure.

Phil's Seat

Bucketty Community installing Phil's Seat


null